FoldaRap, Peer-to-Peer Edition

Finished 09 / 07 / 2013
Accomplished!
Received
€ 52.835
Minimum
€ 12.000
Optimum
€ 16.000
97 Co-financiers
Channel
  • Contributing € 10

    Supporter

    All contributions are welcome and deserve a big thank you ! A nice postcard and some stickers :)

    > 07 Co-financiers
  • Contributing € 20

    Curious

    A random printed part among the trials which permitted to progress in the development of the FoldaRap.

    • previous rewards
    > 06 Co-financiers
  • Contributing € 40

    Explorator

    A little printed object :)

    • previous rewards
    > 00 Co-financiers
  • Contributing € 60

    Collector

    A tee-shirt with an illustration of the FoldaRap for this special p2p-edition

    • previous rewards
    > 02 Co-financiers
  • Contributing € 500

    FoldaRap P2P Edition

    The most interesting reward of this campaign, also probably the quickest way to have your kit!

    All you need to build the lastest version of the FoldaRap, excepted the printed parts.
    Find a local reprapper to add them to your kit !

    (hint : with probably more than 40 000 machines in the wild, there must be one near you, or we can still have them printed separately)

    > 14 Co-financiers
  • Contributing € 600

    FoldaRap full kit

    All you need to build the lastest version of the FoldaRap !

    > 65 Co-financiers
  • Contributing € 900

    Workshop @NYBICC

    Workshop at NYBICC (Nancy, France)

    We find a date that arrange everyone, and you came to build a FoldaRap with us in our super friendly Makerspace : the Nancy Bidouille Construction Club !

    > 05 Co-financiers
  • Contributing € 1.000

    Workshop around the world

    We find a date that arrange everyone to invite me (for a week-end to a full week), and I personally come with my machine to help you build and learn to use the FoldaRap(s) you may have funded !

    > 02 Co-financiers

News of the week (17)

28 | 04 | 2014
News of the week (17)

On a été légèrement ralenti dans notre rythme, il y a une pièce qui tardait à être réapprovisionnée mais on devrait la recevoir cette semaine, et la totalité des kits restants (18) devraient être expédiés aussitôt et en début de semaine prochaine comme prévu, la préparation étant bien rodée à présent :)

--

We were a little slowed in our schedule, a piece is late to restock, but we should have it by the end of the week, and all the kits left (18) should be dispatched just after and at the beginning of the next week as expected, as we are getting better at preparing the kits :)

Yorumlar

Aki
Hace 1 decade
Hello Emmanuel
Its been a long time
Will you also be sending out the bootstrapping kits after you finish these 18 kits ?
EmmanuelG
Hace 1 decade
Indeed ^^'
We will plan this after after yep :)
Ward Wouts
Hace 1 decade
Hi Emmanuel,

We (me and 3 collegues) have started building our kits and everything looks /really/ good right until the point where the instructions say "you're almost done". We're stuck on assembling the hotend. The pneumatic fitting for the hotend is missing and We can't figure out how to fix the fan to the hotend.

The heated bed instructions and the end stop instructions also unclear.

Can you improve the instructions? Preferably quickly as we really want to start printing :) :) :).

EmmanuelG
Hace 1 decade
Hi Ward,

Good to hear :)

I'll send the missing part today, and will have a look to complete the instructions once back from Germany, I know this part is far from perfect ^^'

(otherwise to anyone, feel free to modify/improve the wiki that's the point of having a wiki :) )

Inicia sesión para dejar un comentario